Leakage test: Incorrect operation of gate valves and globe valves
When testing the newly constructed pipeline system, the pipes and valves need to undergo preliminary tests: two leak tests, one 150% static hydraulic test, and one N2He (nitrogen, helium) leak test. The objects of these tests include not only the flanges connecting the valves and pipes, but also the valve covers and valve body interfaces, as well as all the stop valves/valve cores in the valve body.